Stadionul Silviu Ploesteanu construction process

Stage 1: Removal of the existing light tower and installation of the new roof. The main reason the roof is installed first is to maintain lighting on the site. At this point, support pillars for the upper tier stands should be installed to minimise crane requirements later.

Stage 2: The pitch is relocated to its final position, and the eastern lower stand is constructed in the empty space.

Stage 3: Addition of the southern and southeastern stands.

Stage 4: Replacement of the main stand.

View from the other end.

Stage 5: Filling in the northeastern corner, and the construction of the upper eastern stand.

Stage 6: Replacement of the western lower stand.

Stage 7: Construction of the western upper stand.

Stage 8: Work on the western stand structure and final streetscaping works.
Just a hypothetical demonstration of the construction process on the site.