Stage 2: The pitch is relocated to its final position, and the eastern lower stand is constructed in the empty space. |
Stage 3: Addition of the southern and southeastern stands. |
Stage 4: Replacement of the main stand. |
View from the other end. |
Stage 5: Filling in the northeastern corner, and the construction of the upper eastern stand. |
Stage 6: Replacement of the western lower stand. |
Stage 7: Construction of the western upper stand. |
Stage 8: Work on the western stand structure and final streetscaping works. |